President Bola Tinubu’s government has paid N1.23 trillion of the legacy debts it owes power generators, betting that clearing arrears will revive a stalled electricity sector, Joseph Tegbe, Nigeria’s power minister, has said.
The payment represents more than a third of the N3.3 trillion Tinubu approved for verified obligations to generation companies.
Tegbe disclosed the figure at a luncheon with senior editors in Lagos on Friday, where he conceded that Nigerians’ frustration with unreliable supply is justified and that the sector remains far from meeting expectations.
Unpaid bills to generators have long sat at the center of the industry’s dysfunction. Power plants that are not paid struggle to buy gas, maintain equipment and attract fresh investment, which in turn limits how much electricity reaches homes and factories in Africa’s most populous nation.
Read also: Why solar is winning Nigeria’s blackout economy
Clearing the backlog is meant to break that cycle, though roughly N2.1 trillion in approved payments is still outstanding.
Tegbe described the sector’s troubles as systemic rather than isolated. He pointed to gas supply constraints, ageing infrastructure, vandalism, transmission bottlenecks, poor metering and commercial weaknesses running through the entire value chain from generation to the customer’s meter.
Fixing one link, he argued, will not help unless the others improve alongside it, and that calls for disciplined implementation of reforms rather than short-term patches.
The government is also leaning on grid upgrades. Newly commissioned substations and equipment have added more than 1,300 megavolt-amperes to transmission capacity, with work covering Apapa, Ijora, Ikeja, Kumbotoso, Dankata, Mashi, Dan-Agundi, Biliri and Walalambe.
Authorities are building a new National Grid Control Centre in Osogbo to replace a facility more than 60 years old, and are working toward expanding generation capacity to 10,000 megawatts.
On the demand side, more than 2.8 million customers were metered between 2023 and October 2026 under the Presidential Metering Initiative. Inadequate metering has been a persistent source of friction between distribution companies and consumers, and a drag on the revenues that keep the system solvent.
Looking ahead, the ministry plans to build out electricity supply along three economic corridors: Lagos-Ogun, Benin-Enugu-Port Harcourt and Abuja-Kaduna-Kano. The Lagos-Ogun axis and the Abuja franchise area together account for more than half of national electricity demand, and Tegbe said they are the proposed pilot sites for 24-hour energy zones. He cautioned that the pilots depend on technical readiness and commercial viability, a reminder that round-the-clock power is a target rather than a promise. The aim is to match generation, transmission and distribution capacity to demand in the country’s biggest economic centres.
The minister also said the federal government has approved a coordinated anti-vandalism campaign involving security agencies, backed by tougher legal measures to protect power assets. Attacks on gas pipelines and transmission infrastructure have repeatedly disrupted supply.
Tegbe used the encounter with editors to appeal for a working relationship with the press.
He called for reporting grounded in facts and professional scrutiny, and said Nigerians deserve timely explanations when the lights go out, along with clarity on what is being done and which institutions are responsible. The ministry, he said, would keep communication channels open, welcome constructive criticism and issue regular updates on the progress of reforms.
Rebuilding trust may prove as hard as rebuilding the grid. Successive administrations have promised stable power, and many Nigerians and businesses still rely on private generators, an expensive workaround that raises costs across the economy.