Nigeria’s $538m agro-industrial promise must move beyond construction sites – Businessday NG

Nigeria’s agricultural challenge is not simply how to produce more food. It is how to preserve and process what farmers grow and move it to markets where it can earn a return. The Special Agro-Industrial Processing Zones (SAPZ) programme was designed to bring factories closer to farms. Yet five years after approval, its first phase remains far behind schedule. The question is whether government and development partners can turn a sound idea into functioning businesses.

Advertisement
Advertisement

Approved in December 2021, SAPZ Phase I is a $538.05 million programme covering seven states and the Federal Capital Territory. It envisages eight agro-industrial hubs with roads, electricity, water and internet, alongside 15 Agricultural Transformation Centres, irrigated farmland and farm-to-market roads. Private processors are expected to buy produce from surrounding farmers and convert it into goods with greater value and longer shelf lives.

“Delayed projects carry costs beyond missed deadlines. Undisbursed loan balances may attract commitment charges, depending on facility terms. More importantly, Nigeria forgoes the jobs, farm incomes, investment and processing capacity that completed infrastructure should support.”

The African Development Bank (AfDB) estimated in 2021 that 30 to 50 percent of harvests were lost after leaving farms. Without adequate storage, transport and processing, farmers are often forced to sell perishable crops quickly, when seasonal supply depresses prices, or watch them spoil. Processors face uncertain supplies and high power, logistics and storage costs. Consumers ultimately pay through higher prices and dependence on imported processed food.

But an attractive design is not evidence of delivery. The original timetable ran from 2022 to 2026, with completion expected by April 2027. The AfDB envisaged construction reaching 50 percent by the third quarter of 2024 and being largely finished by early 2025. Construction was launched in Kaduna on April 8, 2025. The completion date has since moved to December 31, 2028, according to the government’s development cooperation dashboard and the AfDB’s 2025 country portfolio review.

Read also: Transforming agriculture: Inside Nigeria’s agro-industrial revolution

The implementation record is troubling. In its November 2025 progress report, the AfDB said Kaduna and Cross River had signed contracts for companies to design, build and run their hubs. Oyo was still assessing bids, while Ogun and Imo were completing site selection and environmental studies. Four years after approval, two locations had yet to finalise their sites. The report said implementation had not advanced sufficiently to measure outcomes such as jobs created or post-harvest losses reduced.

Advertisement

Foreign lenders account for $520 million of the $538.05 million financing plan, while federal and state governments are expected to contribute $18.05 million. The AfDB’s November 2025 report showed that only about 8 per cent of its own $210 million package had been disbursed by November 10 that year. This covers the AfDB package, not the entire programme, but illustrates the distance between financing approval and implementation.

Delayed projects carry costs beyond missed deadlines. Undisbursed loan balances may attract commitment charges, depending on facility terms. More importantly, Nigeria forgoes the jobs, farm incomes, investment and processing capacity that completed infrastructure should support. The AfDB’s estimated $8.73 billion in economic benefits over 20 years is a projection, not a return already secured. It depends on factories operating, investors committing capital and farmers supplying produce consistently.

Advertisement

The programme must therefore be judged by commercial readiness, not construction alone. A completed shed is not an agro-industrial hub if electricity and water are unreliable, roads are poor, raw materials are unavailable or processors have not signed up. Investors need predictable rules on land, incentives, environmental standards and infrastructure management. Farmers need transparent supply arrangements, fair prices, inputs and reliable routes to market. Without these conditions, public infrastructure may remain commercially idle.

Expansion before Phase I has demonstrated operational results and requires scrutiny. On December 1, 2025, the AfDB approved an initial $200 million for Phase II, covering 10 more states within a plan to reach 27 states. Overlapping phases are not inherently wrong. But expansion must draw on lessons from the first phase and not assume that approval guarantees success. Later disbursements should, where loan agreements permit, be tied to independently verified milestones: completed hubs, signed private tenants and factories processing produce.

Advertisement
Advertisement

The Federal Ministry of Agriculture and Food Security, state governments and programme offices should publish quarterly scorecards for each hub. These should disclose construction progress, utility connections, counterpart funding paid and outstanding, tenant commitments, processing volumes, jobs created and produce purchased from farmers. Figures should be independently verified, with institutions named as responsible for missed targets. Government should also disclose compensation paid to people affected by land acquisition and publish the legal framework governing the zones.

The AfDB, as a financier, must explain how it is monitoring implementation and responding to delays. Its responsibility should extend beyond disbursement procedures to whether the programme is delivering the outcomes used to justify the loans. Phase II must not become an escape from the accountability owed for Phase I.

SAPZ remains a worthwhile response to Nigeria’s weak farm-to-factory links. But success will not be measured by money approved, states listed or ceremonies held. It will be measured by functioning factories, private investment, produce bought from farmers, jobs sustained and losses reduced. Until those results are visible, the country’s $538 million agro-industrial promise remains unfinished.